Blue-green deployment
Blue-green deployment is a release strategy that keeps two identical production environments. One, say blue, serves all live traffic. The new version is deployed and tested on the idle green environment. Once green passes its tests, the router or load balancer sends all traffic to green at once. Blue keeps running untouched, so going back is the same switch in reverse.
How it works
Deploy v2 to green while blue serves users.
Run smoke tests against green through an internal address.
Point the router at green. All traffic moves in one step.
Leave blue on v1 until v2 has run cleanly under real traffic. Blue then becomes the target for the next release.
A switch at the load balancer takes seconds. A switch through DNS waits for cached records to expire, so with a 300-second TTL some clients reach blue for at least 5 minutes, and longer if they ignore the TTL.
Why it matters in production
Rolling back means pointing the router at the old environment again, which is quick because nothing has to be rebuilt or redeployed. The price is double capacity during the release, and a database both versions can use, so schema migrations must stay backward compatible. Unlike a canary deployment, every user moves at once, so a problem that only appears under full load hits everyone.